Can you describe what goes into creating an initial estimate for a construction project?

An early stage estimate of the project cost differs from a construction budget, as it relies on the contractor’s past experience, and involves some art and some science. It allows the Owner an opportunity to organize funding sources and plan actual expenditures in advance.

When information and plans may not be complete, the estimator must blend known data, such as a building’s size and scope, with other details based on unit costs, assumptions, historical data, and best judgment. As the design is refined, the final budget is based more on solid information.

When creating a preliminary estimate, the estimator first must assess the level of detail of the plans to determine the best method of approaching the estimate. He’ll then assess the site and existing conditions, considering overhead power lines, presence of hazardous materials, site grades, etc. that will require additional scope and labor.

Estimators next must prepare accurate quantity take-offs based on the plans, determining the materials needed and factoring seasonal effects and price trends. The estimator will then extrapolate the associated labor needs, wage rates, and equipment needed to install. Finally, general project requirements such as permitting, insurance and design fees are also incorporated.

Resources

Wisconsin Institute of Plastic Surgery Celebrates Opening of New Clinic and Surgery Center
August 19, 2025
Woodland Resort Celebrates Grand Opening of Shores Venue Event Center
August 19, 2025
Reflecting on Success: Midwest Refrigerated Services
August 6, 2025
Tri Energy Cooperative Cenex Expressway Project is Complete!
July 1, 2025
New Morning Coffee Expansion Project Complete!
July 1, 2025
Consolidated Construction Expands Millwork Division with Neenah Facility
June 25, 2025
Spring Lake Church Expands Ministry To Lawrence; Breaks Ground On New Lawrence Campus Location
June 11, 2025
Local Construction Company Raises $43,000 for Children’s Miracle Network at Annual Company Meeting
May 6, 2025
Marcus Koehl of Consolidated Construction joins New North board
March 5, 2025
Midwest Refrigerated Services Opens Regional Distribution Center, Optimizing Lactalis USA’s Midwest Logistics Network
February 28, 2025
Consolidated Construction Company: Awarded ABC WI Project of the year
January 27, 2025
Midwest Refrigerated Services Breaks Ground on New Regional Distribution Center, Continuing 30+ Year Partnership with Consolidated Construction
February 14, 2024

Recent Comments

    Past News, Events, and Blog Posts